1、Construction of a Deep-Sea Wharf in the Canadian Arctic J. S. Rittberg, EIT,1 H. G. Kullmann, P.Eng., 2 and P. Dubé, P.Eng.3 1,2WorleyParsons Westmar, a division of WorleyParsons Canada Ltd., 400 - 233 West 1st Str

2、eet, North Vancouver, BC, V7M 1B3, Canada; PH (604) 985-6488; FAX (604) 985-2581; emails: jennie.rittberg@worleyparsons.com, harald.kullmann@worleyparsons.com 3Xstrata Nickel, 120 Ave. de l’aéroport, Rouyn-Norand

3、a, QC, J9X 5B7, Canada; PH (514) 825-4988; email: pdube@xstratanickel.ca ABSTRACT The port facility in Deception Bay, located in the remote Nunavik region of the Canadian Arctic, has been operated by Xstrata Nickel for

4、 their Raglan Mine since 1998. The port was originally built in 1971 to service a former asbestos mining operation. In 2003, after 33 years of service, the wharf was identified as in need of a comprehensive repair pro

5、gram in order to maintain it in a safe and operational condition. However, the extent of deterioration was not apparent until a detailed inspection in the summer of 2005 revealed that the structure was suffering from a

6、n aggressive bacterial attack of the steel sheet piles and a localized collapse in the near term was a strong possibility. Emergency repair measures were designed and initiated and the planning for a complete wharf re

7、habilitation program implemented. . Construction of a complete replacement of the wharf structure was scheduled for the summer of 2007. During the project planning phase, it became apparent that due to the global deman

8、d for nickel combined with the limited nickel concentrate storage capacity at Deception Bay, there was intense pressure from the owners to maintain shipping schedules. To avoid any possible disruption to operations, a

9、nd with the added constraint of a four- month ice-free construction window, the conventional construction method of using steel sheet piles for Arctic deep-sea wharves, was no longer a feasible option. In order to meet

10、 all of the commercial and construction limitations and constraints, the only rehabilitation option considered possible within the timeframe was to construct new structures using concrete caissons. This paper presents

11、an overview of the project approach taken and some of the unique features that were incorporated into the design to overcome the inherent problems of working in a remote location, and the project constraints related to

12、 a very short construction window and allowing the mine to continue shipping operations during construction. BACKGROUND The Deception Bay Port is located on the Hudson Strait in the Canadian Arctic in northern Quebec

13、. Built in 1971 for an asbestos mine, the port has served Xstrata 826 Ports 2010: Building on the Past, Respecting the Future © 2010 ASCEPorts 2010 Downloaded from ascelibrary.org by Changsha University of Science

14、all rights reserved.Several key objectives to address the project constraints were considered in almost every aspect of the wharf replacement planning and design. ? Onsite construction hours in the Arctic region were t

15、o be maximized to improve the construction schedule and reduce the crew size to ease pressures on transportation and housing. ? The chain of supply and product export was to be maintained for the nickel mine by allow

16、ing vessel operations throughout the construction window ? Facility installation had to be completed within the short ice-free construction window. WHARF REPLACEMENT SOLUTION In October 2006, the project was approved w

17、ith a budget of $54 million and a planned completion of November 2007. With the final selection of an approved concept, the design team moved quickly to prepare the design package with the intent to issue an early ten

18、der call to general contractors. This would allow for early equipment mobilization on an icebreaking vessel scheduled to arrive on site in January 2007. Figure 1 provides a plan view showing the old and new wharf arra

19、ngements. Figure 1 - Old and New Wharf Arrangements Construction Lodging. A lack of facilities to lodge the crews was identified as a critical hurdle to overcome for successful construction execution. The port site alr

20、eady had a 35 person camp, but more than 50 additional rooms would be required to accommodate the crews required to construct the new wharf. Located 100 km away from the main mine camp by gravel road, the Deception Bay

21、 port was considered too far away to effectively commute workers for each construction shift. After a proposed plan to use a vessel-based camp was abandoned because of sea-ice risks, the project team sought to make us

22、e of a mine camp expansion that was also being executed in 828 Ports 2010: Building on the Past, Respecting the Future © 2010 ASCEPorts 2010 Downloaded from ascelibrary.org by Changsha University of Science all rig

溫馨提示

  • 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
  • 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶(hù)所有。
  • 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
  • 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
  • 5. 眾賞文庫(kù)僅提供信息存儲(chǔ)空間,僅對(duì)用戶(hù)上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶(hù)上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
  • 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
  • 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶(hù)因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。

評(píng)論

0/150

提交評(píng)論