版權說明:本文檔由用戶提供并上傳,收益歸屬內容提供方,若內容存在侵權,請進行舉報或認領
文檔簡介
1、4800 英文單詞, 英文單詞,26500 英文字符 英文字符,中文 中文 8200 字文獻出處: 文獻出處:Bakhshi P , Touran A . An Overview of Budget Contingency Calculation Methods in Construction Industry[J]. Procedia Engineering, 2014, 85:52-60.An overview ofbudget c
2、ontingency calculation methods in construction industryPayamBakhshi,AliTouranAbstractDue to risks and uncertainties associated with construction projects, owner agencies usually add a reserve amount to the estimated proj
3、ect cost. This reserve amount, known as contingency, is to absorb the monetary impact of the risks/uncertainties and to prevent cost overrun. Over the past two decades, many contingency calculation methods for constructi
4、on projects have been introduced by practitioners and researchers. These methods can be ranged from simply considering a percentage of the project base cost to complex mathematical methods. Each of these methods suggests
5、 an approach for calculating contingency using different assumptions. The question is which one of these methods should be applied to a certain project at a specific phase. Knowing the advantages and disadvantages of eac
6、h method can help practitioners in construction industry select the best method based upon their project characteristics, budget, and time. This paper compiles almost all contingency calculations methods and divides them
7、 into three main categories of: (1) deterministic methods, (2) probabilistic methods, and (3) modem mathematical methods. Each of these categories are then divided into more subcategories and discussed in detail.Keywords
8、: Contingency; Budget; Risk; Deterministic; Probabilistic; Monte Carlo Simulation.1. IntroductionOwners usually need to have an accurate early cost estimate for their projects in order to provide sufficient budget for pr
9、ojects. Risks and uncertainties associated with a project are impediments to reach an accurate cost estimate. For instance, nearly 50% of the large active transportation projects in the United States overran their initia
10、l budgets [30]. To overcome the cost overrun issue, identifying project risk factors and cost escalation factors have been the subject of much research [32]. To absorb the cost impact of these risk factors, a contingency
11、 budget is added to the total project budget. This means that a total cost of project is broken down to: (1) base cost, and (2) contingency cost. Base cost is the cost of project which is not including contingency [35].
12、These are certain cost items of a project with a given scope necessary to physically deliver the project. Contingency is defined as a reserve budget for coping with risks and uncertainties and to help keep the projects o
13、n budget. Contingency is traditionally estimated as a predetermined percentage of project base cost depending on the project phase. In recent years, some agencies have started conducting formal probabilistic risk assessm
14、ent to estimate contingency budget rather than deterministic approach [34]. However, to establish the contingency budget, an agency must make all efforts to set aside a budget which is optimized. This becomes more import
15、ant when an agency is dealing with a portfolio of projects. Allocation of an excess budget for a project will use up the money that can be spent on other projects. For instance the current approach used by the U.S. Feder
16、al Transit Administration (FTA) to estimate the contingency budget in transit projects called Top-down Model is based upon a probabilistic method using lognormal distributions for different cost categories in the project
17、. However, the way that cost categories are ranged is very conservative resulting in a contingency budget far larger than what might be indeed needed [7]. In this paper, first several contingency definitions given by dif
18、ferent agencies are presented. Then an Deterministic approaches cannot effectively address the risks specific to a project and consider the unique effects of project complexity, market condition, and location [24]. There
19、fore, deterministic methods can be summarized in two main categories as follows:Fig. 1. Contingency Calculation MethodsPredefined Percentages (Fixed/Line Items): This approach is the simplest method of contingency alloca
20、tion. In this method, either an across-the-board predetermined (fixed) percentage of total project base cost or various percentages of line items will be added to the project budget as contingency. When contingency is ad
21、ded separately for each line item (allocated contingency), it can be an overall contingency as unallocated contingency added to the project budget on top of the allocated contingency. Each agency has its own set of guide
22、line for contingency percentages. The suggested percentages are given for different key phases of a certain type of project and may be a single value or a range of values.Expert Judgment: The only difference of this meth
23、od and predetermined percentage is that in this method there is not a set of predetermined percentages, but an expert or a group of experts with strong experience in risk management and risk analysis define(s) the percen
24、tage of contingency for the project under consideration. Even though this method can relatively considers the specific situation of each project by adding unique percentage for each project but it does not go through a f
25、ormal and comprehensive risk assessment. Therefore, the contingency budget cannot be estimated adequately. Furthermore, similar to predefined percentage method, it does not provide the confidence level for the sufficienc
26、y of the estimated contingency.3.2. Probabilistic MethodsThe main difference between probabilistic methods and deterministic methods is that in probabilistic methods, uncertainties are explicitly modeled using appropriat
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網頁內容里面會有圖紙預覽,若沒有圖紙預覽就沒有圖紙。
- 4. 未經權益所有人同意不得將文件中的內容挪作商業(yè)或盈利用途。
- 5. 眾賞文庫僅提供信息存儲空間,僅對用戶上傳內容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內容本身不做任何修改或編輯,并不能對任何下載內容負責。
- 6. 下載文件中如有侵權或不適當內容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- [雙語翻譯]建筑預算外文翻譯--建筑業(yè)預算應急計算方法綜述(英文)
- [雙語翻譯]建筑預算外文翻譯--建筑業(yè)預算應急計算方法綜述中英全
- 2014年建筑預算外文翻譯--建筑業(yè)預算應急計算方法綜述
- 2014年建筑預算外文翻譯--建筑業(yè)預算應急計算方法綜述.DOCX
- 2014年建筑預算外文翻譯--建筑業(yè)預算應急計算方法綜述(英文).PDF
- [雙語翻譯]預算外文翻譯-預算編制實踐進展--綜述與研究視角
- [雙語翻譯]預算外文翻譯-預算編制實踐進展--綜述與研究視角(英文)
- 項目預算外文翻譯
- [雙語翻譯]碳交易外文翻譯--南非建筑業(yè)的碳排放交易
- 2003年預算外文翻譯-預算編制實踐進展--綜述與研究視角
- 2016建筑業(yè)營改增計算方法
- [雙語翻譯]建筑成本控制外文翻譯--尼日利亞建筑業(yè)的項目成本控制
- 2003年預算外文翻譯-預算編制實踐進展--綜述與研究視角.DOCX
- [雙語翻譯]碳交易外文翻譯--南非建筑業(yè)的碳排放交易(英文)
- [雙語翻譯]建筑成本控制外文翻譯--尼日利亞建筑業(yè)的項目成本控制(英文)
- [雙語翻譯]碳交易外文翻譯--南非建筑業(yè)的碳排放交易中英全
- 2003年預算外文翻譯-預算編制實踐進展--綜述與研究視角(英文).PDF
- [雙語翻譯]建筑成本控制外文翻譯--尼日利亞建筑業(yè)的項目成本控制中英全
- [雙語翻譯]土木工程外文翻譯——建筑業(yè)全面質量管理評估(原文)
- [雙語翻譯]土木工程外文翻譯——建筑業(yè)全面質量管理評估(節(jié)選)
評論
0/150
提交評論